October 29, 2026

IMPROVEMENT WORKS ON A82 NORTH OF AUCH

Updated 29 October: Due to changes in the wider programme of works, resurfacing on the A82 north of Auch will start a week later than planned, on Thursday 3 December. Please see new dates below. Drainage repair works start on Monday 2 November with 24-hour traffic lights in place until Wednesday 18 November Resurfacing works … Continued

October 28, 2026

GROUND INVESTIGATION WORKS AT A82 RUSKICH WOOD

Works start on Monday 2 November 24-hour traffic lights in place until 28 November BEAR Scotland, on behalf of Transport Scotland, is set to carry out ground investigation works on the A82 trunk road at Ruskich Wood, approximately two miles north of Alltsigh. Works will be carried out between the hours of 7am and 7pm, … Continued

October 23, 2026

RESURFACING WORKS ON A82 SOUTH OF RANNOCH MOOR

POSTPONED: Due to Storm Boelo affecting most of Scotland, these works have been postponed. Revised dates will be communicated as soon as they are confirmed. Overnight resurfacing works started on Sunday 26 July Temporary traffic lights with convoy in place BEAR Scotland, on behalf of Transport Scotland, is set to carry out resurfacing at two locations … Continued

October 1, 2026

CYCLE PATH GROUND INVESTIGATION ON A82 NORTH OF ONICH

Works start on Monday 5 October Temporary traffic lights in place for two days BEAR Scotland, on behalf of Transport Scotland, are set to carry out ground investigation works on the cycle path alongside the A82 north of Onich from Monday 5 October. Works will be carried out between the hours of 8am and 6pm … Continued

September 28, 2026

ESSENTIAL MAINTENANCE WORKS ON A82 LEAGANN BRIDGE SOUTH OF LAGGAN LOCKS

UPDATED 06 October 2026: Due to the emergency installation of temporary traffic lights on the A82 at Loch Lochy following a vehicle collision with the roadside safety barrier, these bridgeworks are currently on hold, and will no longer commence on 12 October. Further updates on the repair of the safety barrier and a revised start … Continued

September 24, 2026

UNDERGROUND RADAR SURVEYS ON A82 FORT WILLIAM

Works start on Tuesday 29 September Traffic lights in place until Thursday 1 October BEAR Scotland, on behalf of Transport Scotland, are set to carry out two nights of underground radar surveys at two locations on the A82 in Fort William, Belford Road and Nevis Roundabout, from Tuesday 29 September for two nights. The surveys … Continued

September 22, 2026

A82 ROCK SLOPE STABILISATION WORKS NEAR GROTAIG

Works commence on Monday 28 September 2026 Temporary lane closure in place until Thursday 24 December 2026 BEAR Scotland, on behalf of Transport Scotland, will commence the next phase of rock slope stabilisation works on the A82 near Grotaig, approximately 5.6 km south of Drumnadrochit, on Monday 28 September. To ensure the safety of the … Continued

September 22, 2026

ESSENTIAL TREE FELLING ON A82 AT ARNBURN, SOUTH OF LUSS

Updated 12 October 2026: Tree felling works on the A82 at Arnburn have been completed earlier than planned therefore all traffic management has been removed from site. Works start on Monday 28 September Three weeks of overnight closures with hourly amnesties BEAR Scotland, working on behalf of Transport Scotland, is carrying out essential landscaping work … Continued

September 15, 2026

DRAINAGE INVESTIGATION ON A82 NORTH ROAD, FORT WILLIAM

Drainage investigation starts on Thursday 17 September Temporary traffic lights BEAR Scotland, on behalf of Transport Scotland, will be carrying out essential drainage investigation on the A82 for two nights from Thursday 17 September. The works will be carried out between the hours of 8pm and 6am and are expected to finish on the morning … Continued

August 27, 2026

SIGNAGE REPLACEMENT ON A82 SOUTH OF CRIANLARICH

Signage replacement works start on Tuesday 1 September Temporary traffic lights until Thursday 3 September BEAR Scotland, on behalf of Transport Scotland, is set to install a new direction sign and chevrons on the A82 south of Crianlarich from Tuesday 1 September. The works will be carried out between the hours of 8am and 4pm … Continued

August 25, 2026

DRAINAGE IMPROVEMENTS ON A82 AT ROSE COTTAGE, INVERARNAN

Update on 10 September 2026: Having identified the need for more work than first anticipated, the project on the A82 at Rose Cottage, Inverarnan, will require an additional three days of work, now finishing on Wednesday 16 September. Full details below. Drainage improvements starting on Monday 7 September Temporary traffic lights in place until Wednesday … Continued

August 6, 2026

OVERNIGHT RESURFACING ON THE A82 SOUTH OF URQUHART CASTLE

Updated 18 August 2026: Due to poor weather, resurfacing works on the A82 South of Urquhart Castle did not take place last night and require an extra night. Works will now finish on the morning of Wednesday 26 August. Full details below in red. Works commence on Sunday 16 August Road closure with amnesty periods … Continued