April 29, 2026

ROCKSLOPE STABILISATION CONTINUES ON A82 EAST OF GLENCOE VILLAGE

Rockslope stabilisation works extended until Monday 1 June 24-hour two-way traffic lights with 30mph speed restriction remains in place BEAR Scotland, on behalf of Transport Scotland, is continuing essential rock slope stabilisation works on the A82 Trunk Road at the Meeting of Three Waters, approximately six miles east of Glencoe Village. The project involves vegetation … Continued

April 29, 2026

DRAINAGE INVESTIGATION ON A82 AT ROSE COTTAGE, INVERARNAN

Drainage investigation on Monday 11 May Temporary traffic lights 8am to 4:30pm   BEAR Scotland, on behalf of Transport Scotland, will be carrying out essential drainage investigations on the A82 at Rose Cottage in Inverarnan on Monday 11 May from 8am to 4:30pm.   To protect roadworkers and those using the A82, temporary traffic lights … Continued

April 24, 2026

RESURFACING WORKS ON A82 NORTH OF FORT AUGUSTUS

 Six overnight road closures from Sunday 14 June   BEAR Scotland, on behalf of Transport Scotland, will carry out a programme of resurfacing works on the A82 north of Fort Augustus starting on Sunday 14 June. The works will be undertaken overnight between 8pm and 6am, with no works on Friday or Saturday nights. The … Continued

April 21, 2026

RESURFACING WORKS ON A82 BALLACHULISH ROUNDABOUT

Works start on Tuesday 5 May for three nights Overnight convoy in place for safety   BEAR Scotland, on behalf of Transport Scotland, will carry out overnight resurfacing works on the A82 Ballachulish Roundabout, south of Ballachulish Bridge, starting on Tuesday 5 May. The works will be undertaken overnight between 7pm and 6am each working … Continued

April 17, 2026

RESURFACING WORKS PLANNED ON A82 FORT WILLIAM

Three phases of resurfacing works to start from Sunday 10 May   BEAR Scotland, on behalf of Transport Scotland, will undertake a programme of  overnight resurfacing works on the A82 at three locations in Fort William, beginning on Sunday 10 May.   The works are required to address defects within the existing carriageway and will … Continued

April 8, 2026

RESURFACING WORKS ON A82 NORTH OF CRIANLARICH

Works start on Sunday 12 April for two night Overnight convoy in place until morning of Tuesday 14 April   BEAR Scotland, on behalf of Transport Scotland, will carry out overnight resurfacing works on the A82 north of Crianlarich, near Fillan Bridge, starting from Sunday 12 April.   Works will be carried out between the … Continued

March 27, 2026

RESURFACING WORKS AT A82 RANNOCH MOOR

Update on 9 April 2026: Due to changes in the programme, work on the A82 at Rannoch Moor have now been rescheduled for Summer 2026. New dates will be issued in due course. Night-time resurfacing works start on Sunday 12 April Temporary traffic lights with convoy in place BEAR Scotland, on behalf of Transport Scotland, … Continued

March 26, 2026

ESSENTIAL MAINTENANCE ON TWO A82 SWING BRIDGES

Update on 24 April 2026: Due to extra works needing to take place on the A82 at Fort Augustus swing bridge an additional night of works will now be required to take place tonight. New dates below. Works start on Laggan swing bridge on Monday 20 April Works start on Fort Augustus swing bridge on … Continued

March 18, 2026

ESSENTIAL TREE FELLING WORKS ON A82 SOUTH OF LUSS

Overnight works start on Friday 27 March Road closures with hourly amnesties until morning of Wednesday 1 April BEAR Scotland, on behalf of Transport Scotland, will carry out essential tree‑felling and landscaping works on the A82 near Luss. A number of diseased larch trees beside the trunk road at Arnburn, south of Luss, must be … Continued

March 12, 2026

OVERNIGHT RESURFACING ON A82 NORTH OF CRIANLARICH

Updated 02 April 2026: Due to a poor weather forecast, these works have been cancelled. New dates will be provided later this year. Overnight resurfacing works to take place on Monday 30 March Three-way traffic lights with convoy BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential improvement works on the … Continued

March 2, 2026

GROUND INVESTIGATION WORKS ON THE A82 NORTH OF ONICH

Updated 5 March 2026: Due to changes in the programme of works, ground investigations on the A82 north of Onich have been cancelled. These will be rescheduled for a later date and further information will be shared once known.  Works start on Monday 9 March Two-Way temporary traffic lights in place until Tuesday 10 March … Continued

February 20, 2026

DRAINAGE WORKS ON A82 BETWEEN GLEN GLOY AND LETTER FINLAY

Daytime lane closure for drainage works Monday 23 February to Friday 27 March   BEAR Scotland, on behalf of Transport Scotland, will be carrying out drainage works on the A82 trunk road between Glen Gloy and Letter Finlay.   The works will take place between the hours of 7am and 7pm each day from Monday 23 … Continued