£80,000 SURFACING IMPROVEMENTS PLANNED FOR A95 WEST OF KEITH  

October 29, 2021

Works start Tuesday 2 November for four days     A section of the A95 west of Keith is to benefit from surfacing improvements worth £80,000 with works set to get underway from Tuesday 2 November at 9am. The improvements will address defects in the road surface on the A95 at Hillockhead Wood creating a … Continued

£110,000 OVERNIGHT SURFACING IMPROVEMENTS PLANNED FOR  THE A92 LUTHRIE

October 29, 2021

Works start Wednesday 10 November for three nights   The northbound section of the A92 at Luthrie is to benefit from surfacing improvements worth £110,000, with works set to get underway on Wednesday 10 November at 7.30pm. The overnight improvements will address defects in the road surface on the single carriageway section of the A92 … Continued

NEW £960,000 PROJECT TO REPAIR SCOUR TO A82 KIACHNISH BRIDGE NEAR FORT WILLIAM

October 28, 2021

  Majority of work involves scour repairs within watercourse Minimum impact will be felt by A82 road users Work set to get underway on Monday 1 November A new £960,000 project of essential scour repair works is set to get underway at the A82 Kiachnish Bridge near Fort William next week. Specialist teams will be … Continued

£500,000 OVERNIGHT SURFACING IMPROVEMENTS AT THE A96 PITMACHIE BETWEEN INVERURIE AND INSCH

October 28, 2021

Works start Tuesday 2 November for ten nights A section of the A96 between Inverurie and Insch is set to benefit from surfacing improvements worth £500,000, with works set to get underway from Tuesday 2 November at 7.30pm. The overnight improvements will address defects on the road surface across a 1.8km section of the A96 … Continued

SEASON’S GRITTINGS…

October 27, 2021

BFG – Big Friendly Gritter visits Livingston schools ahead of winter Livingston schoolchildren were greeted by one of BEAR Scotland’s enormous gritters after winning a competition to come up with names for the road maintenance company’s new machines. Both St Ninian’s and Dedridge Primary Schools were excited to see the sheer size of the eight-wheel, … Continued

A83 REST AND BE THANKFUL

October 27, 2021

Wednesday 27 October – 10.10AM   A83 AT REST AND BE THANKFUL TO REOPEN AT 12 MID-DAY FOLLOWING SAFETY INSPECTION A83 to re-open following use of OMR overnight Road to re-open at 12 mid-day under convoy and will remain in use overnight Teams remain onsite monitoring conditions   The A83 at the Rest and Be … Continued

£145,000 OVERNIGHT SURFACING IMPROVEMENTS, A96 LEYS OF DUMMUIES

October 22, 2021

Works start Sunday 24 October over four nights A section of the A96 near Huntly is to benefit from surfacing improvements worth £145,000 with work set to get underway from Sunday 24 October. The improvements will address defects along a 500m section of the A96 at Leys of Dummuies, east of Huntly, creating a safer … Continued

£30,000 OVERNIGHT SURFACING IMPROVEMENTS ON A90 BETWEEN DUNDEE AND PERTH

October 22, 2021

Works start Thursday 28 October for two nights   A section of the A90 southbound between Perth and Dundee is to benefit from surfacing improvements worth £30,000, with work set to get underway on Thursday 28 October at 7.30pm. The improvements will address defects in the road surface on the southbound section of the A90 … Continued

NEW ROAD MARKINGS AT ACHNACLOICH RAIL BRIDGE ESSENTIAL TO REDUCE RISK OF HIGH SIDED VEHICLES COLLIDING WITH BRIDGE  

October 22, 2021

Recently installed road markings on the A85 at Achnacloich Railway Bridge between Oban and Taynuilt are essential in assisting HGV’s to pass through the highest point of the masonry arch to reduce risk of accidental collision. The new road markings installed at Achnacloich are in accordance with current standards and are appropriate for a bridge … Continued

£95,000 DRAINAGE IMPROVEMENTS PLANNED FOR A96 NORTH OF KEITH

October 22, 2021

  Works start Monday 25 October for three weeks     A section of the A96 at North Bogbain, where temporary traffic lights have been in place to protect the carriageway, is to benefit from drainage improvements worth £95,000 with works set to get underway from Monday 25 October. The project will involve teams carrying … Continued