Updated 5 October 2026: Due to changes elsewhere in the programme of works, resurfacing on the A87 between Invergarry and Bun Loyne will now start on Wednesday 14 October. Please see new information below. Works start on Wednesday 14 October Overnight road closures in place until Tuesday 1 December BEAR Scotland, on behalf of Transport … Continued
Overnight carriageway closures 15-27 September and 11- 27 October 2026 Works to replace joints and resurface a section of carriageway on the bridge carrying the M9 over the River Forth between Junctions 10 and 11 are set to begin on 15 September. Transport Scotland’s operating company BEAR Scotland will carry out the project, which requires … Continued
Overnight local road closures 14 to 18 September 2026 Overnight works to replace joints and resurface the carriageway on the bridge carrying Moss Road over the M9 motorway north of Stenhousemuir are set to take place from Monday 14 to Friday 18 September. For the safety of workers and road users, Moss Road will be … Continued
Overnight slip road closures 7, 8 and 9 September 2026 Overnight works to replace damaged bridge joints on the bridge carrying the M9 over the River Almond between Junction 1A and 1 are set to continue on the nights of Monday 7, Tuesday 8 and Wednesday 9 September, with closures of the slip road from … Continued
Overnight carriageway closures 7-10 September 2026 The southbound carriageway of the M90 motorway will be closed for resurfacing and road marking works from M90 Junction 1A (Queensferry) to M9 Junction 1A (Kirkliston). between 20:00 and 06:00 on the nights of 7 to 10 September The road surface will be renewed on the M9 Junction 1A … Continued
Overnight resurfacing works commence Tuesday 15 September Overnight road closures in place for 13 nights BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential resurfacing works on the A702 at Flotterstone, from Tuesday 15 September 2026. The works will involve resurfacing a 1.1km section of the A702, addressing defects in the … Continued
UPDATE 01.09.26: Due to a schedule change in the wider programme, the A7 overnight resurfacing between Canonbie and Langholm will now require two additional nights of works, with completion scheduled by 06:00 on Saturday 26 September. Overnight road closures 14 to 24 September 2026 BEAR Scotland, on behalf of Transport Scotland, will carry … Continued
Updated 24 September 2026: Due to poor weather, resurfacing works on the A86 East of Strathmashie will not go ahead tonight (Thursday 24 September) and will now end on Thursday 1 October. Please see new end date below. Works starting on Wednesday 16 September Road closure with amnesties until Thursday 1 October On behalf of … Continued