Road, foot path and cycle path reopens following emergency rock face works A section of the A828 between Ledaig and Benderloch has been reopened under traffic signal control after BEAR Scotland, working on behalf of Transport Scotland, have completed emergency safety works. Safety concerns were raised after monitoring of the site identified a 25 Tonne area of rock that had cracked and posed a threat … Continued
Works start at 8pm on Friday 15 November Road, foot path and cycle path closed over the weekend Diversion in place via the A85 from Connell to Tyndrum and the A82 through Glencoe to Ballachulish BEAR Scotland, working on behalf of Transport Scotland, will begin emergency works on the A828 between Ledaig and Benderloch, approximately … Continued
Updated 22 November 2024 – Due to a poor weather forecast works on the A828 Kentallan, South of Ballachulish will be delayed by two days. New date below. Works take place on Thursday 14 and Tuesday 26 November Road closure with amnesties in place BEAR Scotland, on behalf of Transport Scotland, are due to carry … Continued
• Works begin on Wednesday 6 November • Overnight road closure with timed access until morning of Thursday 14 November Road users travelling on the A828 south of Appin will benefit from an improved road surface as resurfacing works set to be carried out later this month by BEAR Scotland, operating on behalf of … Continued
Updated 31 October 2024 – Due to changes in the programme, works on the A828 Ledaig will now be completed by the morning of Wednesday 6 November. Works begin on Monday 28 October Daytime convoy from Monday 28 October for four days Overnight road closure with amnesties from Sunday 3 November for three nights … Continued
Update: works on the A828 near Ballachulish have been postponed tonight due to forecast inclement weather, Wednesday 28 February. Please see the revised dates below. Works begin on Thursday 22 February for eight nights Motorists using the A828 will benefit from an improved road surface as resurfacing works are set to take place from Thursday 22 February to … Continued
Media Update: Works on the A828 at two locations have been delayed by one day. Please see the revised dates and additional information in red below. Works to take place at three locations 22 January – 21 February Motorists using the A828 are set to benefit from an improved road surface, with works planned by Transport Scotland’s … Continued
Essential bridge works start Thursday 5 October for 7 nights Seven nights of work are set to take place on the A828 Connel Bridge, five miles northeast of Oban, starting Thursday 5 October 2023. BEAR Scotland – Transport Scotland’s operating company – will carry out a scheduled inspection and street lighting works on the … Continued
Works begin on 13 June for four days. Lane closures with 10mph convoy 7am-7pm. BEAR Scotland will be resurfacing 1000m of the A828 south of Appin, near Creagan, on behalf of Transport Scotland, with four days of work scheduled to begin on Tuesday 13 June. The works will take place from … Continued
Works begin on Sunday 21th May until Tuesday 30th May Overnight road closures (7pm to 7am) except Fridays and Saturdays Motorists using the A828 will benefit from an improved road surface as BEAR Scotland, Transport Scotland’s operating company, are set to begin resurfacing works later this month. The works will take … Continued
Works to take place at four locations 24 April-18 May North of Oban Airport 24-26 April North of Appin 27 April South of Portnacroish 28 April South of the Highland boundary 10-18 May Lane closures with 10mph convoy 7am-7pm Motorists using the A828 are set to benefit from an improved road surface, with … Continued
Project to begin on Monday 13 March for 13 nights Tree felling on the A82, A83, A84, A85 and A887 Overnight lane closures with temporary traffic lights in place for safety, 7pm to 7am BEAR Scotland will be helping ensure the resilience of Scotland’s native species by felling trees affected by Ash Dieback throughout … Continued