UPDATE: Due to subcontractor availability works on the A84 Kildean and Craigforth Roundabouts will now start on Sunday 22 September. New dates below. Road surface repairs begin on Sunday 22 September Night time lane closures in place 8pm to 3am BEAR Scotland, on behalf of Transport Scotland, are set to carry out carriageway repairs … Continued
Drainage Investigation works planned for one night only on Tuesday 20 August Two-way temporary traffic lights between 7:30pm and 6am BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential drainage investigation works on the A84 between the villages of Callander and Doune on Tuesday 20 August. These drainage investigation … Continued
Drainage improvements works are planned for 10 days starting Monday 5 August Temporary three-way traffic lights between 9:30am and 3:30pm BEAR Scotland, on behalf of Transport Scotland will be carrying out essential drainage improvement works on the A84 at Kilmahog, with works planned to commence Monday 5 August. These drainage improvement works will … Continued
Eight nights of overnight closures with hourly amnesties from Monday 10 June BEAR Scotland, Transport Scotland’s operating company, is carrying out necessary landscaping work to remove over 200 diseased larch trees from a location adjacent to the trunk road south of Strathyre after Scottish Forestry issued a Statutory Plant Health Notice (SPHN). The work will … Continued
Sunday 28 April-Friday 3 May 5am Overnight road closure with amnesties The village of Strathyre and a section of carriageway north of Runacraig on the A84 trunk road are set to receive carriageway and road marking enhancements ahead of the busy summer season, improving safety for road users. BEAR Scotland will be … Continued
Overnight closure of A84 in both directions 22 April 2024 The bridge carrying the A84 trunk road over the M9 motorway at Junction 10 Craigforth will be closed for essential repairs on the night of Monday 22 April. Transport Scotland’s operating company BEAR Scotland will carry out the work on joints in the carriageway between … Continued
Resurfacing Wednesday 15 to Friday 24 November No works Tuesday 14 November due to adverse weather Following the successful completion of the first stages of work, on the A84 in Callander, BEAR Scotland, on behalf of Transport Scotland, are set to undertake the final stages of improvements between Ancaster Square and Leny Feus … Continued
Carriageway Resurfacing scheduled from 5-23 November Following the successful completion of the first stage of works, on the A84 in Callander, BEAR Scotland, on behalf of Transport Scotland, are set to undertake the next stage of improvements between Ancaster Square and Leny Feus from Sunday 5 November. The project, valued at £460,000, will resume … Continued
Works begin on Sunday 28 August for five nights Overnight road closures, 8pm to 7am On behalf of Transport Scotland, BEAR Scotland will be carrying out surfacing improvements on the A84 between Kildean and Craigforth Roundabouts in Stirling, with works set to get underway on Sunday 28 August. The surfacing improvements will greatly improve … Continued
Project to begin on Tuesday 16 August for seven nights Overnight road closures to be implemented 16 and 17 August, 8pm to 5am Overnight convoy to be operated from 18 to 24 August, 7pm to 5am No works to be undertaken on Friday or Saturday nights. On behalf of Transport Scotland, BEAR Scotland will … Continued
Project set to begin on Wednesday 15 June for one night Overnight road closure in place for safety, 8pm to 6am An essential surfacing project on the A84 north of Doune worth £10,000 is set the take place on Wednesday 15 June. The project will see a section of the A84 at Buchany resurfaced … Continued
Works get underway on Monday 23 May for three months A new £100,000 project of essential scour repair works is set to get underway at the Bridge of Teith on the A84 near Doune from Monday 23 May. The works are expected to take up to three months to complete. Work to the bridge … Continued