August 26, 2025

ESSENTIAL ROCKSLOPE REMEDIATION WORKS TO TAKE PLACE ON A82 AT ALLTSIGH

Weekday works to start Monday 1 September for 5 weeks   For five weeks from Monday 1 September, essential remedial works will take place each weekday, on the rock slope along a stretch of the A82 at Alltsigh. Carried out by BEAR Scotland on behalf of Transport Scotland, a two-way traffic light system will be … Continued

August 8, 2025

CARRIAGEWAY IMPROVEMENTS ON A82 AT TARBET

Update on 21 August: Works on the A82 at Tarbet will now require an additional three nights of works due the length of the scheme being extended to including the A82/A83 Junction. Works will now be complete on the morning of Thursday 28 August. Carriageway works to start on Sunday 17 August Convoy with temporary … Continued

July 28, 2025

OVERNIGHT ROAD SAFETY IMPROVEMENTS AT A82 LOCH TULLA COTTAGES

Night working 7pm to 6am from Sunday 3 August Temporary traffic lights until the morning of Saturday 13 September BEAR Scotland, on behalf of Transport Scotland, are carrying out road safety improvements on the A82 at Loch Tulla Cottages. From Sunday 3 August, the overnight works involve replacing safety barriers on the verges.   Works … Continued

July 17, 2025

OVERNIGHT SURFACING ON A82 BRIDGE OF ORCHY

Update 4 August 2025: Due to the Met Office amber weather warning, works on the A82 Bridge of Orchy are cancelled tonight (Monday 4 August). Works are planned to resume on Tuesday 5 August. Please see new dates below.   Works begin on Sunday 3 August for three nights Overnight road closures in place until … Continued

June 27, 2025

OVERNIGHT RESURFACING ON A82 INVERGARRY

Update 8 July 2025: Due to resources being required elsewhere, overnight road resurfacing on the A82 Invergarry will now start on Monday 14 July. Please see new dates below.   Works start on Monday 14 July Overnight road closures in place until the morning of Friday 18 July BEAR Scotland, on behalf of Transport Scotland … Continued

June 16, 2025

OVERNIGHT SURFACING ON A82 SOUTH OF DRUMNADROCHIT

Update 27 June 2025: Due to delays elsewhere in the programme caused by poor weather conditions, surfacing works on the A82 south of Drumnadrochit will now start on Tuesday 1 July. Please see new dates below.   Surfacing works from Tuesday 1 July until Thursday 3 July Road closure between 8pm and 6am with amnesties … Continued

June 11, 2025

OVERNIGHT SURFACING ON A82 NEVIS ROUNDABOUT

Works start on Monday 30 June until the morning of Thursday 3 July Overnight lane closures in place for duration of works   BEAR Scotland, on behalf of Transport Scotland are set to carry out overnight surfacing improvements on the A82 at Nevis Roundabout, Fort William, from Monday 30 June.   Works will be carried … Continued

May 23, 2025

OVERNIGHT DRAINAGE IMPROVEMENTS ON A82 ACHINTORE ROAD, FORT WILLIAM

Works starting on Monday 16 June Lane closure between 8pm and 6am   On behalf of Transport Scotland, BEAR Scotland will be carrying out essential drainage improvements on the A82 Achintore Road, at the south end of Fort William with works beginning on Monday 16 June.   The project will take place over five nights, … Continued

May 23, 2025

DRAINAGE INVESTIGATION WORKS ON A82 NORTH OF ARDEN ROUNDABOUT

Drainage investigations works starting Wednesday 28 May Temporary traffic lights   BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential drainage investigation works on the A82 North of Arden Roundabout.   These drainage investigation works will continue for 15 working nights between the hours of 7.30pm and 6am, with no working … Continued

May 20, 2025

DRAINAGE WORKS ON A82 LUSS TO CULAG

Drainage works starting Tuesday 27 May Temporary traffic lights 7:30pm to 6am BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential drainage works on the A82 between Luss and Culag, starting on the evening of Tuesday 27 May.   These drainage works will take place between the hours of 7:30pm and … Continued

April 30, 2025

DRAINAGE INVESTIGATION ON A82 LOCH LOMOND

Drainage investigations works start on Monday 12 May Temporary traffic lights between 7:30pm and 6am   BEAR Scotland, on behalf of Transport Scotland, is set to carry out essential drainage investigation works on the A82 Loch Lomond, between Stoneymollan Roundabout and Arden Roundabout.   These drainage investigation works will be carried out between the hours … Continued

April 29, 2025

ROCK SLOPE WORKS AT A82 LOCH OICH

Update 17 June 2025: Due to adverse weather conditions during the project and additional works being required, rock slope improvements on the A82 at Loch Oich will now be completed by Sunday 29 June.  Project begins on Thursday 8 May 2025 BEAR Scotland, acting on behalf of Transport Scotland, will carry out significant improvement works … Continued