October 2, 2025

RESURFACING THE M80 NORTHBOUND, NORTH OF HAGGS

Overnight carriageway closures 20, 21 and 22 October 2025 The northbound carriageway of the M80 motorway between Junction 7 (Haggs) and Junction 8 (Bankhead) will be closed for resurfacing on the nights of 20, 21 and 22 October, between the hours of 19:30 and 06:00. Transport Scotland’s operating company BEAR Scotland will carry out the … Continued

October 2, 2025

M80 JUNCTION 9 NORTHBOUND OFF-SLIP CLOSURE FOR SURVEY

Overnight slip road closure Monday 6 October 2025 The slip road exiting the northbound M80 at Junction 9, Pirnhall, will be closed between 22:30 and 02:00 on the night of Monday 6 October, to allow a detailed survey of the road surface to be carried out. A diversion route will be signposted via the M9 … Continued

September 30, 2025

CARRIAGEWAY REPAIRS ON THE M80 SOUTHBOUND BETWEEN JUNCTIONS 9 AND 8

Overnight carriageway closures 13 and 14 October 2025 The M80 southbound will be closed at Junction 9 between 20:30 and 06:00 on the nights of Monday 13 and Tuesday 14 October. This is to allow Transport Scotland’s operating company BEAR Scotland to repair defects in the carriageway. A signed diversion route for traffic wishing to … Continued

June 30, 2025

INVESTIGATION WORKS ON M80 NORTHBOUND JUNCTION 9 OFF-SLIP

Overnight slip road closure 7 July 2025 BEAR Scotland, Transport Scotland’s operating company, is set to carry out investigation works in advance of future resurfacing on the M80 Junction 9 northbound off-slip. To allow the works to be carried out safely, the slip road will be closed between the hours of 20:30 and 06:00 on … Continued

June 10, 2025

M80 JUNCTION 9 NORTHBOUND OFF-SLIP CLOSURE FOR SURVEY

UPDATE 19 June 2025: To avoid a clash with planned works at M9 Junction 10, the diversion route for these works will now be via the M9 northbound to turn at Junction 11, Keir Roundabout, before returning southbound to exit via the Junction 9 southbound off-slip. Overnight slip road closure Friday 20 June 2025 The … Continued

May 20, 2025

RESURFACING THE M80 SOUTHBOUND BETWEEN JUNCTIONS 9 AND 8

UPDATE 3 June 2025: Works on the M80 southbound between Junctions 9 and 8 will now take place on the nights of both Tuesday 3 and Wednesday 4 June, following disruption to the programme due to adverse weather. Four overnight carriageway closures from 29 May 2025 The southbound carriageway of the M80 motorway between Junctions … Continued

May 13, 2025

M80 OVERNIGHT MAINTENANCE

Overnight carriageway closures 18-23 May 2024 A six-night programme of overnight maintenance on the M80 between Junctions 8 and 9 is scheduled to begin on Sunday 18 May. Transport Scotland’s operating company BEAR Scotland will use these closures to carry out a variety of routine maintenance tasks and to tidy up the carriageways and roadsides, … Continued

February 7, 2025

CARRIAGEWAY REPAIRS ON THE M876 SOUTHBOUND

Overnight carriageway closure Friday 14 February 2025 The M876 southbound will be closed at Junction 1 between 19:30 and 06:00 on the night of Friday 14 February. This is to allow Transport Scotland’s operating company BEAR Scotland to repair defects in the carriageway. A signed diversion route for traffic on the M876 southbound will be … Continued

January 23, 2025

DRAINAGE WORKS ON THE M80 NEAR BANNOCKBURN

UPDATE 7 February 2025: Works on the M80 J9 northbound off-slip were completed ahead of schedule last night, therefore the slip road will remain open tonight. Overnight slip road closures Thursday 6 and Friday 7 February 2025 The slip road exiting the M80 northbound at Junction 9, Pirnhall, will be closed between 19:30 and 06:00 … Continued

December 14, 2024

M80 JUNCTION 9 SLIP ROAD REOPENS FOLLOWING SUBSIDENCE REPAIR

Temporary reduced speed limits no longer in force Works to repair subsidence in the slip road exiting the northbound M80 at Junction 9 have been completed. The road is now open to traffic as normal and temporary speed restrictions on the M80 are no longer in force. The slip road was closed for safety on … Continued

November 14, 2024

M80 JUNCTION 9 SLIP ROAD SUBSIDENCE REPAIR

Overnight slip road closures for four weeks, commencing Monday 18 November 2024 Works to repair subsidence in the slip road exiting the northbound M80 at Junction 9 will commence on Monday 18 November. The slip road was closed for safety on 28 June, as a result of significant subsidence in the carriageway. Since August, traffic … Continued

November 8, 2024

MAJOR RESURFACING WORKS ON THE M80 NEAR DENNY

UPDATE 26 November 2024: The programme for these works has been revised following delays caused by Storm Bert: The current contraflow will remain in place 24 hours a day until 19:30 on Thursday 28 November The northbound carriageway will be closed from 19:30 until 06:00 and the southbound carriageway will be closed from 22:00 until … Continued