December 24, 2025

A83 LOCHNELL STREET LOCHGILPHEAD TO REOPEN

The A83 at Lochnell Street in Lochgilphead is reopening today (24 December) around 1:00pm under traffic signal control. Lochnell Street has been closed since the fatal house fire on Sunday 14 December and its re-opening followed the completion of works to stabilize the affected building using a temporary scaffold and support system. The traffic management … Continued

December 23, 2025

RESURFACING WORKS AT M8 JUNCTION 4A WHITBURN

Overnight road closures 7-13 January 2026 BEAR Scotland, acting on behalf of Transport Scotland, will carry out essential resurfacing works on the westbound carriageway of the M8 between Junction 4A-5, at Whitburn, between 7 – 13 January 2026 for 5 nights. To ensure the safety of the workforce and road users it is necessary to … Continued

December 23, 2025

A9 RAIGMORE INTERCHANGE IMPROVEMENT WORKS TO START

Updated 6 January 2026: Due to ongoing discussions with our subcontractor to finalise details of the programme and the industry shutdown over the festive period, these works are now scheduled to begin on Monday 19 January.  We are reviewing the construction programme to identify any tasks which can be completed more quickly in order to … Continued

December 19, 2025

A68 DRAINAGE WORKS SOUTH OF JEDBURGH

UPDATE 14 January 2026: Works on the A68 south of Jedburgh have been completed ahead of schedule, therefore no road closures are required tonight or for the rest of the week. Daytime traffic lights 12 January to 13 February 2026 Overnight road closures 12 to 16 January 2026 Construction works to improve drainage on the A68 … Continued

December 19, 2025

A83 CLOSURE IN LOCHGILPHEAD FOLLOWING FATAL HOUSE FIRE

HGVs are required to use the strategic diversion route as works continue to stabilise the damaged building High sided vehicles over 13’9” should liaise with Police Scotland BEAR Scotland are currently working in collaboration with Argyll and Bute Council and Argyll Community Housing Association (ACHA) following a tragic fatal house fire in Lochnell Street Lochgilphead … Continued

December 19, 2025

BEAR CARES: £59,000 DONATED TO GOOD CAUSES IN 2025

Scotland’s leading road maintenance company BEAR Scotland has donated £59,000 to good causes in 2025, a new report reveals. Over 100 organisations across Scotland have benefitted from the generosity of the company and its staff, with money raised for a variety of charities, community initiatives and schools. Highlights include: Over £25,000 raised for Cash For … Continued

December 18, 2025

RESURFACING WORKS ON A85 AT DALMALLY

Update on 19 January 2026: Due to poor weather, works on the A85 at Dalmally now require and extra day of works and will finish in th evening of Wednesday 21 January. Please see new dates below. Daytime resurfacing works starting Monday 12 January 2026 Convoy in place until Wednesday 21 January 2026    BEAR … Continued

December 18, 2025

CARRIAGEWAY IMPROVEMENTS ON THE A9 SOUTH OF LUNCARTY

Updated 16 January 2026: Due to unforeseen issues onsite, work on the A9 on the southbound on slip at Luncarty now requires an extra night of works that will take place on Sunday 18 January. Please see new dates below.   Carriageway works starting Monday 12 January for four nights Southbound on-slip road closed with diversion … Continued

December 18, 2025

M9 CANAL BRIDGE WORKS BETWEEN JUNCTIONS 6 AND 7

UPDATE 23 January 2026: Daytime lane closures between Junctions 6 and 7 will be removed ahead of schedule, at 06:00 on the morning of Thursday 29 January. Click here for updated details. Fast lane closures in both directions 19 January to 19 February 2026 Overnight southbound carriageway closure 19 January 2026 Overnight northbound carriageway closures … Continued

December 18, 2025

OVERNIGHT RESURFACING WORKS A835 KINKELL TO CONON

Updated on 9 January 2026: Due to the forecast for snow, works in the A835 between Kinkell and Conon will now start on Monday 12 January. Please see new dates below. Resurfacing starting on Monday 12 January Lane closure with convoy between 8pm and 6am   On behalf of Transport Scotland, BEAR Scotland will be … Continued

December 18, 2025

WORKS ON A87 CARRICH BRIDGE

Works start on Monday 5 January 2026 Single lane closure in place for approximately four weeks Pedestrians rerouted onto footpath on opposite side of the bridge BEAR Scotland, on behalf of Transport Scotland, are set to carry out works to install an electrical duct on A87 Carrich Bridge (the approach viaduct to the east of … Continued

December 18, 2025

MAJOR WORKS TO REPLACE RETAINING WALL ON THE A835 AT LOCH GARVE

Works start on Monday 26 January 2026 Single lane closure with two-way traffic lights in place until November 2026   BEAR Scotland, with a significant investment of approximately £2.8 million from Transport Scotland, are set to replace the retaining wall and install new safety barriers on the A835 at Loch Garve. The site is situated … Continued