The installation of a new controlled pedestrian crossing continues to progress on the A9 through Main Street, Golspie. The project will enhance safety and accessibility for residents and visitors alike.
Works carried out so far include laying electrical cables, adding kerbing and tactile paving, and installing a built-out kerb area.
Overnight road resurfacing will be carried out from Tuesday 5 May between the hours of 7.30pm and 6am under three night shifts. To ensure the safety of the workforce and members of the travelling public, a temporary road closure will be in place with amnesties at 8.30pm, 9.30pm, 10.30pm, 11.30pm, 12.30am, 2.30am and 4.30am to allow traffic to safely pass through the work site. Road surfacing is expected to be completed by 6am on Friday 8 May.
Road lining works will be carried out from Monday 11 May to Friday 15 May. In addition, the footway surfacing works have been extended by around 30 metres to reduce ponding issues on the existing pavement. This additional work means works are currently expected to be completed by Friday 22 May. The final commissioning of the crossing will then take place after appropriate road safety checks have been carried out.
The project follows a series of detailed traffic, pedestrian, and topographical surveys carried out within Golspie. These assessments identified a clear need for a safer and more convenient crossing point on the A9, particularly during peak times.
Michael Baxter, BEAR Scotland’s North West Improvements Scheme Manager said: “The team continue to make good progress on the puffin crossing works in Golspie. Extending the pavement surfacing will address existing ponding issues, providing a smoother finish and more user-friendly environment for pedestrians in Golspie.
“Our teams will carry out the remaining works efficiently, with safety as our top priority. The nature of the works will result in an increase in noise levels, and we apologise in advance for the inconvenience this may cause, and thank the local community and road users for their patience and understanding.”
All works are dependent on the weather. As such, the programme of works may change in the event of adverse weather conditions or unforeseen circumstances.
Consultation has taken place with relevant stakeholders in advance of these works to make them aware of the traffic management arrangements and to minimise any inconvenience.
Real time journey information is available from Traffic Scotland on www.traffic.gov.scot, X @trafficscotland or on the mobile site my.trafficscotland.org.