RENEWING ROAD MARKINGS AND ROAD STUDS ON THE M90

March 30, 2022

  • Two-week programme commenced 27 March 2022

A two-week programme of overnight road marking improvement and stud replacement is under way on the M90 between Junctions 1B and 3. Work commenced on Sunday 27 March and is being carried out in 10 phases, with a combination of overnight lane closures and slip road closures in each phase.

Transport Scotland’s operating company BEAR Scotland is using these closures to replace the current road markings with Weatherline road markings. Weatherline is more retroreflective, skid resistant and durable than the current road markings. Any defective or missing road studs will also be replaced.

During week one, overnight works are taking place on the M90 northbound carriageway from Junction 1B to Junction 3, using lane closures on the main carriageway and slip road closures with signed diversion routes. Week two will see a similar approach on the southbound carriageway.

As well as lane closures on the main carriageway, the following slip road closures will be in place from 20:00 until 06:30 each night:

Start
End
Location
Duration
Traffic mgt
Diversion route
27 Mar
28 Mar
M90 NB ~3km North of Jct 2 to Jct 2A
1 night
Junction 2A NB off-slip closed
Junction 3 & A92
28 Mar
29 Mar
M90 NB Jct 2 to ~3km South of Jct 2A
1 night
Junction 2 NB off-slip closed
M90 SB, Jct 1C & M90 NB
29 Mar
2 Apr
M90 NB Jct 2A to 3
3 nights
Junction 3 NB off-slip closed
Junction 2A, A92, Cowdenbeath Jct & A92
3 Apr
4 Apr
M90 SB Jct 3 to 2A
1 night
Junction 3 SB on-slip closed
A92, Cowdenbeath Jct, A92/M90
4 Apr
5 Apr
M90 SB ~3km North of Jct 2 to Jct 2A
1 night
Junction 2A SB on-slip closed
A92 Crossgate Jct & M90 Jct 3
5 Apr
6 Apr
M90 SB Jct 2 to ~3km South of Jct 2A
1 night
Junction 2 SB off-slip closed
M90 SB, Jct 1C & M90 NB
6 Apr
7 Apr
M90 NB Junction 2 to Junction 1B
1 night
Jct 1B off-slip, Jct 1C off-slip & on-slip and Jct 2 on-slip closed
Jct 1C SB off-slip: M90 Jct 2 off-slip A823, B980 & A985
Jct 1C & 2 SB on-slips: M90 NB, M90 Jct 3 & M90 SB
7 Apr
8 Apr
M90 NB Junction 2 to Junction 1B
1 night
Mainline closed
Jct 1B off-slip and on-slip
8 Apr
9 Apr
M90 NB Junction 1B to Junction 2
1 night
Jct 1B on-slip, Jct 1C off-slip, Jct 1C on-slip and Jct 2 off-slip closed
A832, Pitreavie Roundabout & A832 Jct 2A NB.

 

Consultation has been carried out with emergency services and other relevant stakeholders to share information about the project in advance.

Tommy Deans, BEAR Scotland’s South East Network Manager, said: “It’s essential for safety that we close lanes and slip roads while these works are carried out, however we will keep the M90 mainline open to reduce delays as much as possible.

“We’ve split the works into 10 phases to minimise the volume of closures on any one night, reduce delays on the main carriageway and increase work efficiency.

“If you are planning to use the M90 at night over the next two weeks, our advice is to check what restrictions will be in place and allow extra time for your journey if necessary.

“We thank road users and the local community for their patience and understanding.”

Real time journey information is available from Traffic Scotland on www.trafficscotland.org, twitter at @trafficscotland or the mobile site my.trafficscotland.org.