On behalf of Transport Scotland, BEAR Scotland will be carrying out essential road surfacing improvements at four locations on the A889 between Dalwhinnie and Catlodge, from Thursday 8 October.
The project will be carried out in four phases, with the road closures generally implemented between Monday and Friday nights, with one Sunday night closure also planned for North of Dalwhinnie Quarry on 18 October.
|
Dates |
Location |
Traffic Management |
Diversion routes |
|
|
08/10/2026 – 16/10/2026 (19:00 – 06:00) (6 nights) |
North of Crubenmore Junction |
Overnight road closure |
Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa |
|
|
18/10/2026 – 20/10/2026 (19:00 – 06:00) (2 nights) |
Dalwhinnie Junction |
Three-way temporary traffic lights and 10mph convoy |
No diversion |
|
|
20/10/2026 – 22/10/2026 (19:00 – 06:00) (2 nights) |
North of Dalwhinnie Quarry |
Overnight road closure |
Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa |
|
|
22/10/2026 – 04/11/2026 19:00 – 06:00 (9 nights) |
North of Halfway House |
Overnight road closure |
Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa |
Steve Taylor, BEAR Scotland’s North West Design Manager, said: “This resurfacing project will address defects at four locations to provide safer and smoother journeys for road users.
“Our teams will work overnight to complete these improvements as efficiently as possible while keeping disruption to a minimum. We thank the local community and road users for their patience while the works are carried out.
“We encourage road users to plan their journeys in advance and check Traffic Scotland for the latest travel information.”
All works are weather dependent and may be rescheduled if conditions are unsuitable.
Real-time journey information is available from Traffic Scotland at www.traffic.gov.scot, on X @trafficscotland or via my.trafficscotland.org.