A889 RESURFACING BETWEEN DALWHINNIE AND CATLODGE

September 24, 2026

  • Overnight resurfacing works begin Thursday 8 October

  • Works will take place at four locations

  • Overnight road closures and signed diversion required for three phases

  • Project scheduled for completion by Wednesday 4 November

On behalf of Transport Scotland, BEAR Scotland will be carrying out essential road surfacing improvements at four locations on the A889 between Dalwhinnie and Catlodge, from Thursday 8 October.

The project will be carried out in four phases, with the road closures generally implemented between Monday and Friday nights, with one Sunday night closure also planned for North of Dalwhinnie Quarry on 18 October.

Dates                              

Location

Traffic Management

Diversion routes

08/10/2026 – 16/10/2026

(19:00 – 06:00)

(6 nights)

North of Crubenmore Junction

Overnight road closure

Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa

18/10/2026 – 20/10/2026

(19:00 – 06:00)

(2 nights)

Dalwhinnie Junction

Three-way temporary traffic lights and 10mph convoy

No diversion

20/10/2026 – 22/10/2026

(19:00 – 06:00)

(2 nights)

North of Dalwhinnie Quarry

Overnight road closure

Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa

22/10/2026 – 04/11/2026

19:00 – 06:00

(9 nights)

North of Halfway House

Overnight road closure

Traffic diverted via the A9 to Kingussie, then the A86 through Newtonmore to Laggan, and vice versa

Access through the works for emergency services and scheduled bus services will be maintained throughout.

Steve Taylor, BEAR Scotland’s North West Design Manager, said: “This resurfacing project will address defects at four locations to provide safer and smoother journeys for road users.

“Our teams will work overnight to complete these improvements as efficiently as possible while keeping disruption to a minimum. We thank the local community and road users for their patience while the works are carried out.

“We encourage road users to plan their journeys in advance and check Traffic Scotland for the latest travel information.”

All works are weather dependent and may be rescheduled if conditions are unsuitable.

Real-time journey information is available from Traffic Scotland at www.traffic.gov.scot, on X @trafficscotland or via my.trafficscotland.org.