OVERNIGHT SURFACING IMPROVEMENTS ON A9 NORTH OF BOGBAIN

November 19, 2026

  • Works start on Tuesday 1 December

  • Lane closure with convoy and slip-road closure in place

On behalf of Transport Scotland, BEAR Scotland will be carrying out essential road surfacing improvements on the southbound carriageway of the A9 north of Bogbain from Tuesday 1 December.

Works will be carried out between the hours of 8pm and 6am with all surfacing works expected to be completed by 6am on Friday 11 December, subject to weather conditions.

To ensure the safety of both workers and road users, overnight lane closures will be in place with a convoy system to safely escort traffic through the works area. The slip roads will also be closed for the duration of the works, with signed diversion routes in place. Traffic management will be removed outwith working hours, however a temporary 30mph speed limit will remain in place.

Those wishing to use the southbound off-slip will be diverted via the A9 southbound, the B851, B9006 and the B9177.

Likewise, road users looking to make use of the southbound on-slip will be diverted the B9177, A9 northbound, and A96 then back onto the A9 southbound

Access through the works site for emergency services will be maintained at all times.

Steve Taylor, BEAR Scotland’s North West Design Manager said: “This crucial surfacing project on the A9 north of Bogbain will fix existing defects and significantly enhance the driving experience for all road users.

“Our teams are committed to carrying out these works safely and efficiently. We thank the local community and road users for their patience while we complete the improvements.

“To minimise delays, we recommend that motorists plan their journeys in advance by consulting the Traffic Scotland website for real-time travel updates.”

Real time journey information is available from Traffic Scotland on www.traffic.gov.scot, or on X @trafficscotland