A828 Ledaig Rockslope Stabilisation

Major rockslope stabilisation works are progressing at A828 Ledaig following a series of rockfall incidents at this location. The project began in January 2025 and is being delivered to improve long-term safety and resilience along this key route.

The works include vegetation removal, rock scaling, installation of netting to mitigate against rockfall, and targeted intervention for any unstable material.

Background

Following increasing rockfall activity and detailed inspections carried out in late 2024, areas were identified as showing significant deterioration since the previous assessment earlier in the year.

Emergency boulder removal works were undertaken in November 2024 where airbags were used to safely dislodge unstable rock which posed a risk to the carriageway below. Steel plates and a stone bund were utilised to protect the road and underground utilities.

The main rock face  stabilisation programme was subsequently brought forward in response to the rockfall events to ensure public safety and minimise future disruption.

Challenges

The main rock face works commenced in January 2025 and resulted in 4925m² of rock netting being provide and 1196 m of rock bars installed to help stabilise the natural rock.

Environmental and geological issues slowed progress on site and resulted in the requirement for additional interventions, leading to a significantly longer programme of works than originally expected.

Issues with roosting birds also impacted progress despite steps being taken in advance to minimise disruption to local wildlife, including the installation of bird nesting boxes and the use of sound and visual deterrents.

Furthermore, due to the complex geology at this location, developing a safe and effective solution required detailed assessment and careful planning. As our teams have gained safer access to the slope, additional areas of instability have been identified. Expanding the project scope is therefore essential to address these hazards properly and to ensure the long‑term safety and resilience of this key route.

Current status

The current phase of essential rockslope stabilisation works is progressing well and expected to be completed by the end of August 2026, subject to favourable weather conditions and continued progress on site.

On the northern section of the rockslope, installation of the rockfall protection mesh is now largely complete, with the remaining rock anchors currently being installed.

Minor works are still required to complete the stitching of the mesh. Once complete, this will allow the temporary barrier systems used during construction to be removed.

 

Next steps

Following completion of the current activities, work at the site will pause while BEAR Scotland’s geotechnical specialists finalise the design for the next and final phase of the project. 24-hour traffic lights will remain in place during this period to maintain the safety of both road users and the workforce.

Further information on the final phase of the scheme will be shared in the coming weeks once proposals have been confirmed.

Summary

The A828 Ledaig slope has a long history of rockfall activity, and the works being undertaken are essential to ensuring the long-term safety and reliability of this important route.

While unexpected conditions have required an expansion of the project scope, these findings are typical for complex rock environments and can only be fully inspected and assessed once protection systems are in place.

We remain committed to completing the works as efficiently and safely as possible, and minimising disruption to residents, businesses, and road users.

Further information will be issued once the additional design work is complete and the programme for future activity is established.

Latest news

UPDATE ON ROCKSLOPE STABILISATION WORKS ON A828 LEDAIG

Rockslope stabilisation works set to recommence   BEAR Scotland, on behalf of Transport Scotland, is continuing rockslope stablisation works on the A828 between Ledaig and Benderloch, approximately two miles north of Connel Bridge.   The next phase of works is currently underway and is expected to last for up to

Learn more

UPDATE ON ROCKSLOPE STABILISATION ON A828 LEDAIG

Rockslope stabilisation works continue Existing traffic light remain in place until works are completed   BEAR Scotland, on behalf of Transport Scotland, continues rockslope stabilisation works on the A828 between Ledaig and Benderloch, just north of Connel Bridge.   The existing traffic lights at this location will remain in place

Learn more

ROCKSLOPE STABILISATION WORKS PLANNED ON THE A828 BETWEEN LEDAIG AND BENDERLOCH

Rockslope Stabilisation Works, Starting Monday 27 January 2025, for up to 14 weeks Continuous traffic lights with a 30mph speed restriction 10 minute periods of all red traffics will take place during critical periods BEAR Scotland, on behalf of Transport Scotland, are set to carry out Rockslope Stabilisation Works on

Learn more

UPDATE ON OVERNIGHT WORKS REQUIRED ON A828 LEDAIG

Overnight works planned from Monday 15 June Traffic held in both directions for short periods   BEAR Scotland, on behalf of Transport Scotland, is advising road users that rescheduled overnight works on the A828 between Ledaig and Benderloch, approximately two miles north of Connel Bridge, will be carried out from

Learn more